As a project manager notified of an emergency operation plan implementation, what is the immediate priority?

Study for the ASHE Certified Healthcare Constructor (CHC) Exam. Our quiz offers flashcards and multiple choice questions with hints and detailed explanations. Get prepared for your certification!

The immediate priority for a project manager notified of an emergency operation plan implementation is to cease work and contact the owner's representative for further instructions. This action is crucial because the owner’s representative typically has the authority and the knowledge of the specific situation and protocol in an emergency. They are responsible for overseeing the project's alignment with the facility's operations and safety protocols, ensuring that the project's continuation is not detrimental to the situation at hand.

By reaching out to the owner’s representative, the project manager can gain clarity on the severity of the emergency, understand the procedures that need to be followed, and receive guidance on how to safely manage construction activities in light of the emergency. This ensures that all actions taken are in compliance with facility policies and that all stakeholders are aware of the situation.

Ceasing work is important to prevent any potential hazards or complications that might arise during the emergency, but the next step of contacting the owner's representative is essential for directed and effective response measures. Proper communication channels are vital to ensure safety and continuity in a healthcare setting, particularly when emergencies arise.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy